Obi Ezeocha project update
Summary Breakdown of Expenditure on Obi Ezeocha Project at Afor-Ukpor as at 21st August 2019 Architectural Design of Obi Ezeocha-#35,000 Clearing of site-#6000 Digging of foundation/pillars-#6500 Sand (2trips)-#18000 Stone (1trip)-#30,000 Block (1100)-#143,000 Water-#4000 Cement (26bags)-#63,700 20pcs 10mm Iron rod-#36,000 15pcs 1/4 iron rod-#7,500 Nail (4&5 inches-#6,500 Woods; 22, 23, 24, 112, 1*6, bamboo for pillars, […]