Summary Breakdown of Expenditure on Obi Ezeocha Project at Afor-Ukpor as at 21st August 2019

  1. Architectural Design of Obi Ezeocha-#35,000
  2. Clearing of site-#6000
  3. Digging of foundation/pillars-#6500
  4. Sand (2trips)-#18000
  5. Stone (1trip)-#30,000
  6. Block (1100)-#143,000
  7. Water-#4000
  8. Cement (26bags)-#63,700
  9. 20pcs 10mm Iron rod-#36,000
  10. 15pcs 1/4 iron rod-#7,500
  11. Nail (4&5 inches-#6,500
  12. Woods; 22, 23, 24, 112, 1*6, bamboo for pillars, beams, roofing & scaffolding-#150,750
  13. Binding/plate wire-#3000
  14. Mason/Labour/casting of pillars & beam-#54,395
  15. Trimming trees within works environment-#5000
  16. Capentery works to present point-#35,000
  17. Tap for tank-#1,100
  18. Iron bender -#8,000
  19. Transportation for wood-#1,500
  20. Call card-#4,100
  21. Welfare for workers-700
  22. Transportation by PG-#20,000
    Total = #639,745.00.

New donations received:

Update on Donations:

  • Chief kelechi Nnaeto #10,000
  • Obinna Nduezere Nwosu #10,000
  • Ekene Udezuo #50,000

Thank you and more blessings to our brothers.

We are still working to complete this project before the new yam festival Iri Ji ofuo 2019

 
Spread the love

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes:

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>